Home NewsReal EstateMahaRERA Rejects Homebuyer’s Additional Compensation Claim

MahaRERA Rejects Homebuyer’s Additional Compensation Claim

MahaRERA rejects a Pune homebuyer’s additional delay compensation claim after accepting Gera Developments' full and final settlement.

by Constro Facilitator

The Maharashtra Real Estate Regulatory Authority (MahaRERA) has dismissed a homebuyer’s complaint seeking additional compensation for delayed possession of an apartment in Pune, ruling that a homebuyer who voluntarily accepts compensation from a developer as a full and final settlement cannot subsequently claim further compensation without establishing that the settlement was accepted under protest. The authority observed that the homebuyer had accepted the developer’s payment without reserving the right to pursue additional claims or submitting supporting documents indicating disagreement with the settlement.

The complaint was filed against Pune-based Gera Developments Private Limited in connection with its Planet of Joy Project II. The homebuyer had booked an apartment through a registered agreement for sale dated June 10, 2022. Under the agreement, the developer was required to hand over possession by December 31, 2025. The total consideration for the apartment was ₹81.13 lakh, of which the homebuyer had paid approximately ₹77.07 lakh, accounting for nearly 95% of the agreed amount.

However, the developer obtained the building’s part occupancy certificate (OC) on May 29, 2026, after the agreed possession deadline. It subsequently communicated the readiness to hand over the apartment on June 2, 2026, and the homebuyer took possession on June 20, 2026.

Before taking possession, the homebuyer approached MahaRERA on May 31, 2026, seeking possession, the necessary approvals and interest for delayed possession under Section 18 of the Real Estate (Regulation and Development) Act, 2016. She claimed that the possession delay amounted to 171 days and sought interest from January 1, 2026, until the actual handover on June 20, 2026.

The homebuyer also disputed the developer’s compensation offer of ₹30,984, stating that the amount had been calculated for only 27 days of delay. She argued that accepting possession of the apartment did not mean that she had waived her statutory entitlement to compensation for the entire delay period.

Developer’s Explanation for the Delay

In its defence, Gera Developments attributed the delay in obtaining the occupancy certificate to administrative and jurisdictional changes involving the Pune Metropolitan Region Development Authority (PMRDA) and Pune Municipal Corporation (PMC). According to the developer, the transition affected the processing of statutory approvals and contributed to the delay in receiving the necessary certificate.

The developer stated that it had applied for the occupancy certificate on January 27, 2026, after completing the required construction and compliance procedures. The certificate was subsequently granted on May 29, 2026, following directions issued by the Bombay High Court.

The company also informed the authority that possession had been offered on June 2 and handed over on June 20, 2026. It further stated that certain interest charges imposed on delayed instalments had been waived as a goodwill gesture, without admitting liability.

Regarding the compensation claim, the developer maintained that ₹30,984 had been calculated and offered towards the delay period without prejudice to its rights and contentions. It also argued that delays attributable to statutory and administrative processes beyond its control should be excluded while determining its liability.

MahaRERA’s Order

In its order dated November 13, 2026, MahaRERA observed that the homebuyer had voluntarily accepted the compensation offered by the developer towards full and final settlement of the delay claim. The possession documents submitted before the authority did not contain any reservation of further claims, and the homebuyer had not produced evidence establishing that the settlement was accepted under protest.

The authority clarified that the dismissal was based on the voluntary acceptance of the settlement and not merely on the fact that the complaint was filed after the occupancy certificate was issued or that possession had subsequently been accepted. Since the compensation had been accepted as full and final settlement without any recorded objection, MahaRERA concluded that no further relief remained.

Accordingly, the authority dismissed the homebuyer’s complaint against Gera Developments. The order highlights the importance of documenting objections and reserving further claims when accepting delayed-possession compensation from developers