Gurugram Builder Directed to Pay ₹50 Lakh by HRERA

by Constro Facilitator

The Haryana Real Estate Regulatory Authority (HRERA) has ordered Ramprastha Promoter & Development Pvt. Ltd. to pay ₹50 lakh as compensation, along with 11% annual interest, to a homebuyer for the prolonged delay in handing over a residential unit in its Edge Tower project at Sector 37D, Gurugram. The order comes after the buyer waited nearly 13 years without receiving possession of the apartment.

According to the authority’s order, the complainant, Vinod Kumar Gupta, booked the residential unit in 2010 for approximately ₹49.8 lakh. As per the builder-buyer agreement, possession of the apartment was scheduled to be handed over by August 31, 2012. However, the project remained incomplete well beyond the committed timeline, leaving the buyer without possession for several years.

The homebuyer had earlier approached HRERA seeking a refund of the amount paid to the developer. In October 2022, the authority directed the developer to refund the deposited amount along with the applicable interest. Subsequently, Gupta filed a separate complaint before the adjudicating officer, seeking compensation for financial losses caused by the delay, mental harassment, and litigation expenses.

During the proceedings, the developer failed to appear before the authority despite being served notice. Consequently, the adjudicating officer, Rajender Kumar, proceeded ex parte on July 3 after striking off the developer’s defence due to non-appearance.

While passing the order, HRERA observed that the project had remained incomplete for more than six years beyond the promised possession date and that neither a completion certificate nor an occupation certificate had been obtained. The authority referred to the Supreme Court’s judgment in Ireo Grace Realtech Pvt. Ltd. vs Abhishek Khanna & Others, which held that a homebuyer cannot be expected to wait indefinitely for possession after making substantial payments to a developer.

The adjudicating officer also considered the complainant’s submission that he had taken loans, including a gold loan, to meet payment obligations towards the apartment. The authority observed that if the same amount had been invested in another comparable residential project during the intervening years, the investment would likely have appreciated substantially, resulting in a significant financial opportunity loss for the buyer.

Taking these circumstances into account, HRERA awarded ₹50 lakh as compensation for the prolonged delay. In addition, the authority directed the developer to pay ₹1 lakh towards mental harassment and ₹50,000 as litigation costs. The order further states that the compensation amount will carry 11% annual interest from the date of the order until the payment is made.