Chennai Metro Rail’s first operational stretch of Phase 2 is set to open on October 11, with Prime Minister Narendra Modi expected to inaugurate the 14.6 km Poonamallee Bypass-Vadapalani corridor during his visit to Tamil Nadu.
The elevated corridor forms part of Chennai Metro’s wider 118.9 km Phase 2 expansion programme. The opening comes around seven months after the corridor received regulatory approval and will add a new section to the city’s expanding metro network.
The Poonamallee Bypass-Vadapalani section, identified as part of the Yellow Line, will connect Poonamallee Bypass with Vadapalani through 11 operational stations. The corridor is expected to improve connectivity between western Chennai and established transport and residential areas around Vadapalani.
11 Stations to Serve the Corridor
The operational section will include stations at Poonamallee, Mullaithottam, Karayanchavadi, Kumananchavadi, Kattupakkam, Iyyappanthangal, Thelliyaragaram, Porur Bypass and Porur Junction, along with the Vadapalani connection.
Six double-decker stations on the route will initially be bypassed. These include Alapakkam, Karambakkam, Valasaravakkam, Alwarthirunagar, Saligramam and Avichi School.
These stations are expected to be opened at a later stage as the relevant infrastructure and operational requirements are completed.
The corridor is part of the larger Phase 2 network being developed by Chennai Metro Rail Limited (CMRL). The overall Phase 2 project is planned to expand metro connectivity across several parts of Chennai through multiple corridors.
15 Trains Planned on the Route
CMRL will operate 15 trains on the newly opened corridor, with services planned at intervals of 10 minutes.
The scheduled service frequency is expected to provide regular connectivity for passengers travelling between Poonamallee and Vadapalani. The introduction of the corridor will also provide interchange opportunities for passengers travelling towards other parts of Chennai through the existing metro network.
The fare for journeys on the corridor will range from ₹10 to ₹40, depending on the distance travelled.
Passengers travelling onward to Chennai Airport, Chennai Central or Egmore through an interchange at Vadapalani will be charged a fare of ₹50, according to the reported fare structure.
First Operational Stretch of Phase 2
The opening of the Poonamallee Bypass-Vadapalani corridor marks the entry of Chennai Metro’s Phase 2 project into passenger operations.
The wider Phase 2 expansion covers 118.9 km and is intended to extend the metro network to several areas that currently have limited access to rapid public transport.
The new corridor is expected to provide an additional public transport option for commuters in western Chennai, including residents and workers in areas around Poonamallee, Porur and Vadapalani.
The route also connects with the existing metro system at Vadapalani, allowing passengers to continue their journeys towards other major destinations without relying entirely on road-based transport.
With 15 trains planned at 10-minute intervals, the new service will add capacity to Chennai’s metro network while extending rail-based connectivity further west.
The remaining stations on the corridor and other sections of Phase 2 are expected to become operational in stages as construction, approvals and other requirements are completed.