Sunday, April 28, 2024
HomeNewsTop News‘Rapid road’ on OMR to be finally opened for traffic today

‘Rapid road’ on OMR to be finally opened for traffic today

The 500-metre stretch of ‘rapid road’ on Old Madras Road in C.V. Raman Nagar will finally be thrown open for traffic today after missing earlier deadlines. The pilot project, which was taken up by the Bruhat Bengaluru Mahanagara Palike (BBMP) was supposed to be completed in three days, but it took 13 days for completion. The road sees a large volume of traffic every day including inter–State transport vehicles.

The pilot project, which was taken up by the Bruhat Bengaluru Mahanagara Palike (BBMP) was supposed to be completed in three days, but it took 13 days for completion. The road sees a large volume of traffic every day including inter–State transport vehicles.

The repair work was announced on November 23 and the technology comprises the fabrication of concrete slabs (20 feet in length and 5 feet in width) which would be embedded on the road after being prepared in a factory and also the repair of footpaths and ramps.

The deadline was the key with this ambitious project. As opposed to the traditional white-topping work which takes around 30 days, this was going to get over quickly. However, the delay of work caused severe inconvenience to the motorists as they had to take detour when the road was closed for work. 

When the pilot project was announced, civic officials had said that while white-topping roads takes around 30 days, with the new method, around 150 metres of road could be relaid in a day. The rapid method involved pre-cast concrete slabs that are 20 feet long and five feet wide, prepared in a factory and embedded in the road. The project also involves fixing ramps and footpaths. BBMP Chief Commissioner Tushar Giri Nath had earlier said the new method costs about 20-25% more than white-topping.

The deadline was the key with this ambitious project. As opposed to the traditional white-topping work which takes around 30 days, this was going to get over quickly. However, the delay of work caused severe inconvenience to the motorists as they had to take detour when the road was closed for work. 

The BBMP officials said last week that the ‘rapid road’ work was completed according to the earlier deadline, but only small works were left which delayed the opening of the road for vehicle movement.

RELATED ARTICLES

Most Popular

Hot News