The National Highways Authority of India (NHAI) has completed the land acquisition process, including paper possession, for the proposed eight-lane Nashik Phata-Khed (Rajgurunagar) elevated corridor near Pune. With the land-related hurdles addressed, construction is expected to begin within six to eight weeks, marking progress on the long-pending infrastructure project aimed at improving connectivity and reducing traffic congestion along the Pune-Nashik Highway.
NHAI awarded the contract for the elevated corridor to the selected bidder on October 28, 2026. However, construction will begin after the completion of the remaining contractual and financial formalities. According to NHAI officials, the selected company will need to arrange project financing through banks or other financial institutions following the issuance of the letter of intent and work order. The agreement will then be executed before construction activities can commence.
NHAI official Aniket Yadav said the process is expected to take approximately one-and-a-half to two months. He also noted that repeated changes in the project alignment and planning had contributed to delays.
The project was initially planned in 2019-20 as a six-lane highway with service roads, underpasses and flyovers. However, the original tender was cancelled due to the proposed Chakan metro project, which required changes to the infrastructure planning. Subsequently, the elevated corridor was proposed following directions from the Union minister, bringing additional requirements related to land acquisition and project execution.
The revised plan aims to provide an eight-lane elevated road along the Nashik Phata-Khed stretch, addressing traffic congestion on one of the important routes connecting Pune with industrial and commercial areas towards Chakan and Rajgurunagar. The corridor is expected to improve traffic movement, reduce travel delays and support connectivity for commuters and freight vehicles.
The Maharashtra government has also extended financial support to facilitate the project. A government resolution issued on July 17, 2025, approved assistance covering Goods and Services Tax (GST) reimbursement, land acquisition expenses and royalty concessions. These measures were intended to address financial requirements associated with the infrastructure development.
Further discussions on funding arrangements took place during a meeting held on July 14, 2026. The meeting considered the possibility of routing land acquisition funding through the Maharashtra State Road Development Corporation (MSRDC) and the National Highways wing of the state Public Works Department (PWD).
While preparations for the elevated corridor move forward, NHAI will continue maintaining the existing National Highway 60 (NH-60). The authority will address potholes, waterlogging, road maintenance and traffic management issues. It will also oversee the maintenance of road signage and lighting to ensure safer movement until the new infrastructure becomes operational.
Yadav indicated that the project could be completed within the next three years, provided there are no further delays or implementation-related obstacles. He emphasised that completing land acquisition and planning requirements before construction would help avoid future complications and prevent public expenditure on infrastructure that might subsequently require demolition.
The Nashik Phata-Khed elevated corridor has faced delays for nearly six to seven years since its initial planning. With the contract awarded and land acquisition completed, the project has moved closer to the construction stage. Once implemented, the eight-lane corridor is expected to improve traffic capacity, strengthen regional connectivity and support the movement of people and goods along the Pune-Nashik Highway.