Bombay HC Sets Deposit Condition in Lodha-MMRDA Dispute

by Constro Facilitator

The Bombay High Court has granted a conditional stay on the execution of an arbitral award directing the Mumbai Metropolitan Region Development Authority (MMRDA) to pay Rs 238 crore to Lodha Developers Ltd. The compensation was awarded to the developer for losses arising from a reduction in the permissible built-up area of its proposed commercial project at Wadala Truck Terminal in Mumbai.

The High Court directed MMRDA to deposit Rs 145 crore with the court within six weeks for the stay to remain effective. The amount represents the principal compensation and 50% of the compensation awarded. The stay will continue until the final disposal of MMRDA’s petition challenging the arbitral award.

MMRDA had approached the Bombay High Court seeking an unconditional stay on the execution of the arbitral award dated October 17, 2025, passed by a sole arbitrator. However, Justice NJ Jamadar, who heard the matter, declined to grant unconditional relief, observing that there was nothing inherently wrong with the arbitral award to justify such an order.

The dispute between MMRDA and Lodha Developers originated from the development rights offered for a commercial project at Wadala Truck Terminal. In March 2010, MMRDA invited bids for a 25,000 sq m plot with a permissible built-up area of 4.95 lakh sq m. The land was offered on a 65-year lease, with a reserve price of Rs 50,000 per sq m. The development was subject to height clearance from the Civil Aviation Department of the Government of India.

Lodha Developers emerged as the successful bidder with an offer of Rs 81,818 per sq m, taking the total premium to approximately Rs 4,050 crore. The developer had based its bid on the understanding that the proposed development would be eligible for the stated built-up area of 4.95 lakh sq m.

However, the project subsequently faced restrictions on its permissible height. Lodha Developers had proposed an iconic 101-storey tower for the Wadala plot and sought special clearance for a height of 530 metres. The Airports Authority of India (AAI), however, granted clearance for a height of only 131.56 metres. This significantly reduced the proposed tower’s height and the number of floors that could be developed.

The reduction in permissible development area affected the project’s commercial viability and led to disputes between the developer and MMRDA. The developer invoked the arbitration clause in the agreement, seeking compensation for the financial losses arising from the restrictions.

While determining the compensation, the arbitrator considered the losses incurred by Lodha Developers due to the cancellation of bookings for 287 flats proposed above the 42nd floor. The calculation also included the developer’s loss of profit resulting from the reduced development potential.

The arbitrator concluded that the tender notice issued by MMRDA amounted to misrepresentation and was fraudulent within the meaning of the relevant provisions of the Contract Act. The award held that the developer had been induced to enter into the contract and submit a higher bid based on the representation that the entire permissible built-up area of 4.95 lakh sq m would be available for development.

During the proceedings, the Bombay High Court observed that the nature of the representation made by MMRDA in the offer document was central to the dispute. It also noted that the arbitrator’s findings could neither be considered perverse nor facially untenable.

The court further observed that Lodha Developers had submitted its bid at a higher rate of Rs 81,818 per sq m based on the development potential represented in the tender document. Considering these circumstances, the High Court was not inclined to grant MMRDA an unconditional stay on the arbitral award.

The conditional order provides interim relief to MMRDA from immediate execution of the full award while requiring it to deposit Rs 145 crore within the stipulated six-week period. The final outcome will depend on the High Court’s decision on MMRDA’s petition challenging the arbitral award.