Home NewsRegulatoryApproval Delays Stall 100 Real Estate Projects in Kolkata

Approval Delays Stall 100 Real Estate Projects in Kolkata

by Constro Facilitator

Nearly 100 real estate projects covering an estimated 15 million sq ft of proposed development and involving investments of around Rs 7,500 crore have been stalled across Kolkata’s Salt Lake, Sector V and New Town growth corridor due to delays in statutory approvals since February 2026.

The approval process across the Bidhannagar Municipal Corporation (BMC), New Town Kolkata Development Authority (NKDA) and Nabadiganta Industrial Township Authority (NDITA) has remained largely inactive, according to industry representatives. The delays have affected projects of different sizes, including residential developments, commercial properties, plot-based construction, renovation proposals and bungalow redevelopment.

The affected locations include Salt Lake, Rajarhat, Gopalpur, Mahishbathan, VIP Road and adjoining areas. Developers said the pending proposals range from developments on 4-5 cottah plots to larger residential and commercial projects.

According to industry members, building plan approvals, revised sanctions and completion certificate-related applications have not progressed since the assembly election process began. The situation has continued even as the Kolkata Municipal Corporation (KMC) recently resumed its clearance process, with its Municipal Building Committee approving 15 projects.

Developers said the approval delays have affected several areas within New Town, including allotted plots and fringe locations along routes 91 and 211, particularly around the ITC Infotech area. Projects in adjoining panchayat areas that require NKDA’s approval and technical assessment have also been affected.

The prolonged delay has disrupted project planning and execution, with developers unable to proceed with financial closures, marketing activities and construction mobilisation in several cases. Industry representatives said the absence of timely clearances has affected both ongoing development plans and proposed investments across the urban growth corridor.

The impact extends beyond real estate developers. Construction workers, contractors, building material suppliers, consultants and other businesses associated with project development are also facing difficulties due to the slowdown in approvals. Industry members said the lack of project activity is affecting employment and business opportunities across the construction supply chain.

Civic authorities are also facing revenue implications. Developers pointed out that delays in project approvals have slowed the collection of approval fees, development charges, GST and other payments linked to construction activity. The longer projects remain pending, the greater the possibility of additional costs and contractual complications.

Industry representatives have also raised concerns about the impact on investor confidence. The New Town-Rajarhat-Salt Lake belt has emerged as a major urban expansion zone around Kolkata, attracting residential and commercial investments. Delays in building sanctions, revised approvals and completion certificates could affect the pace of development in these locations.

Developers have called for clarity on the approval mechanism and the resumption of regular processing across BMC, NKDA and NDITA to prevent further delays and cost escalations.

Meanwhile, calls and messages to Ravi Agarwal, who is serving as BMC chairman and NKDA chief executive and is associated with the NDITA board, remained unanswered.

Industry representatives said the timely restoration of the approval process would be important for restarting stalled projects and supporting construction activity across Kolkata’s expanding real estate corridor.