Sunday, April 28, 2024
HomeInfrastructureTunnelConstruction Methods for Underground Metro Tunnels

Construction Methods for Underground Metro Tunnels

Metro serves as a primary mode of public transportation, catering to the majority of commuters in major cities due to its efficiency, safety, and convenience. As demands increase, major cities are consistently expanding their metro systems, leading to the construction of additional metro lines. The selection of an appropriate construction method is paramount, considering the unique characteristics of each project. It is crucial to balance the functionality of the metro engineering itself with the efficient utilization of both above and below-ground space. Simultaneously, minimizing the negative impact of metro construction on the surrounding environment is imperative.

The construction method chosen significantly affects various aspects, including the line embedment, the structural design of metro stations, and the overall construction period, which directly influences project costs and societal, economic, and environmental benefits.

Underground Metro Tunnel construction

Metro tunnel construction involves the excavation and construction of tunnels for metro or subway systems. It typically includes digging underground passages to accommodate train tracks, stations, and other infrastructure. The construction process typically includes the following key steps:

1. Survey and Planning:

   – Conducting surveys to determine the optimal route and depth for the tunnels. Engineers consider factors such as geological conditions, existing infrastructure, and the desired connectivity.

2. Geotechnical Investigations:

   – Assessing the soil and rock conditions along the tunnel route to understand the challenges and plan for necessary reinforcements.

3. Excavation and Lining:

   – Excavating the tunnel using the TBM or other excavation methods. Simultaneously, installing tunnel lining or segments to reinforce the tunnel walls and prevent collapses.

4. Utility Relocation:

   – Relocating existing utilities (such as water, gas, and electricity lines) that may be in the path of the tunnel.

5. Installation of Rail Tracks and Infrastructure:

   – Placing tracks for metro trains and installing electrical systems, signaling equipment, and other necessary infrastructure within the tunnel.

6. Ventilation Systems:

   – Implementing ventilation systems to ensure proper air circulation and maintain air quality within the tunnel.

7. Safety Features:

   – Incorporating safety features, including emergency exits, fire protection systems, and communication systems to ensure passenger safety.

8. Testing and Commissioning:

   – Conducting extensive testing of the tunnel and metro systems to verify their functionality, safety, and efficiency.

9. Integration with Metro Network:

    – Connecting the newly constructed tunnel with the existing metro network to ensure seamless operations.

Throughout the entire process, engineers and construction teams work diligently to overcome geological challenges, ensure structural integrity, and adhere to safety standards. Metro tunnel construction plays a crucial role in expanding urban transportation networks, reducing traffic congestion, and providing efficient public transit options.

It is important to carefully choose the appropriate construction method for each project. Priority must be given to balance the functionality of the metro engineering itself with the efficient utilisation of both above and below-ground space. Simultaneously, minimizing the negative impact of metro construction on the surrounding environment is imperative. The construction method chosen significantly affects various aspects, including the line embedment, the structural design of metro stations, and the overall construction period, which directly influences project costs and societal, economic, and environmental benefits.

The Tunnel Boring Machine (TBM) method is a modern tunneling technique that involves the use of specialized machines to excavate tunnels. These massive machines bore through the ground, simultaneously removing soil or rock and installing tunnel support. TBMs are particularly advantageous in urban areas due to their ability to minimize surface disruption and facilitate faster construction. They are versatile, suitable for various ground conditions, and are commonly employed for the construction of long tunnels, such as those in metro systems.

Tunnel Boring Machine

TBM excavation begins with the machine’s cutting head breaking through the tunnel face, simultaneously excavating soil or rock. The excavated material is transported through the machine via a conveyor system. As the TBM advances, precast concrete segments are installed to form the tunnel lining.

The New Austrian Tunnelling Method (NATM) is a tunnel construction approach that combines drill and blast techniques with immediate tunnel support. This method allows for flexibility and adaptability to varying geological conditions. It involves the use of shotcrete and rock bolts to provide immediate support to the tunnel walls. NATM is advantageous for its ability to accommodate real-time adjustments during construction, making it suitable for tunnels in diverse ground conditions, including both rock and soil.

New Austrian Tunnelling Method

NATM involves a cyclical process of excavation and support. Initially, the tunnel face is drilled and blasted, creating a void. Immediately after, a layer of shotcrete (sprayed concrete) is applied to stabilize the tunnel walls, followed by the installation of rock bolts for additional support. This sequence is repeated as the tunnel progresses, allowing for adaptability to varying geological conditions.

The Cut and Cover method is a  tunneling method involving the excavation of a trench, construction of the tunnel within the trench, and subsequent covering of the tunnel. This approach is cost-effective and straightforward, making it suitable for shallow tunnels. It is often employed in urban areas where tunnel depth is relatively shallow, and surface disruption needs to be minimized. The Cut and Cover method is a practical choice for projects where the construction process can be executed with simplicity and efficiency.

Cut and Cover method

The Cut and Cover method begins with the excavation of a trench at the tunnel location. The tunnel structure is then constructed within the trench, and the trench is backfilled to cover the tunnel. This method is particularly effective for shallow tunnels, and it is often employed in urban areas where disruption to surface activities needs to be minimized.

The Shield Tunneling method employs a shield to support the tunnel face during excavation, preventing ground collapse. This technique is particularly useful in urban environments with soft or unstable ground conditions. The shield provides a protective structure for workers and equipment, enhancing safety during tunnel construction.

Shield Tunneling involves the use of a shield, a protective structure that supports the tunnel face during excavation. The shield is equipped with mechanisms to remove excavated material and install tunnel support simultaneously. Workers operate within the shield’s safety of the chamber.

Fore Poling  utilizes vertical poles installed ahead of the tunnel face. These poles act as temporary supports to prevent collapse during excavation. Workers install the poles in a systematic manner to create a stable structure. While historically significant, Fore Poling has been largely replaced by more advanced support methods in modern tunneling.

The Linear Plate method utilizes steel plates to support tunnel walls during excavation. This technique is suitable for softer ground conditions where additional stability is required. The steel plates act as a protective structure, preventing collapses and ensuring the integrity of the tunnel. The Linear Plate method is used when ground stability is a primary concern, particularly in areas with softer soils or other challenging geological conditions.

In the Linear Plate method, steel plates are installed along the tunnel walls to provide support during excavation. These plates act as a protective lining, preventing collapses and ensuring the stability of the tunnel. The plates are typically bolted or secured in place as the tunnel progresses.

the factors to consider for selecting the right metro tunnel construction methods in bullet points:

  • Soil Conditions:
    • Soil composition and stability
    • Water table levels
  • Geological Characteristics:
    • Rock formations
    • Presence of fault lines
  • Urban Density:
    • Proximity to existing structures
    • Impact on surface traffic and utilities
  • Environmental Impact:
    • Minimization of ecological disruption
    • Mitigation of noise and vibration
  • Project Timeline:
    • Construction speed and efficiency
    • Meeting deadlines and milestones
  • Cost:
    • Initial construction costs
    • Long-term maintenance expenses
  • Safety Regulations:
    • Adherence to local safety standards
    • Emergency evacuation considerations
  • Ground Settlement:
    • Potential impact on surface structures
    • Mitigation measures
  • Infrastructure Disruption:
    • Impact on existing utilities
    • Measures to minimize service interruptions
  • Metro System Requirements:
    • Tunnel diameter and depth
    • Compatibility with rail systems
  • Feasibility Study:
    • Engage experts for a comprehensive analysis
    • Evaluate alternatives and their pros/cons

The demand for metro tunnels in India is driven by several factors

  • Rapid Urbanization
  • Traffic Congestion Mitigation
  • Efficient and Fast Transportation
  • Urban Development Integration
  • Coping with Population Growth
  • Integration with Public Transit

The evolution of metro tunnel construction methods showcases a dynamic blend of technological advancements and engineering prowess. From the traditional cut-and-cover method to state-of-the-art tunnel boring method, each approach contributes to the efficiency, safety, and sustainability of metro infrastructure. As cities continue to grow, the continuous upgradation of these methods becomes paramount for creating resilient, interconnected, and environmentally conscious transportation networks.

RELATED ARTICLES

Most Popular

Hot News