Friday, April 19, 2024
HomeNewsRailway NewsCantonment Railway Station to undergo a two-phase makeover

Cantonment Railway Station to undergo a two-phase makeover

Also, a Foot Over Bridge is being constructed. It would connect Borebank Road to Netaji Road for the comfort of passengers.

Bengaluru Cantonment, one of the oldest railways stations on the South Western Railway (SWR) network, is undergoing a makeover, informed the Indian Railways.

The project is being executed in EPC (Engineering-Procurement-Construction) mode and a single agency is responsible for planning, procurement, and execution of all the aspects of the project. 36 months is the targeted date of completion. On December 12, 2022, the Letter of Award (LoA) was awarded in favour of M/s Varindera Construction Pvt Ltd, New Delhi.

In the first phase, at Rs 45 crores, the Bengaluru Cantt station’s yard is being remodelled. Two additional island platforms are being constructed. Three additional lines are also being constructed which would enable the operation of the increased number of trains from/to this station. Hence, will ease the pressure on KSR Bengaluru railway station. By February 2023, the remodelling of the Bengaluru Cantt railway yard is targeted to be done.

Also, a Foot Over Bridge is being constructed. It would connect Borebank Road to Netaji Road for the comfort of passengers. 

In the second phase, at a cost of Rs 480 crores, the station building will be redeveloped. This will make Bengaluru Cantt a world-class airport-like terminal. The railway station would be redeveloped as a ‘City-Centre’. However, the forthcoming structure will preserve the existing heritage elements of the historic building. The architectural elevation attempts to capture the spirit of the Bengaluru city.

RELATED ARTICLES

Most Popular

Hot News